USER’S GUIDE
Managed Rack PDU
98
Resetting Peak Load and kWh
Path: Device Manager > Device Load
1. Click the Device Manager tab, then device load from the Load Management
menu.
2. Click the Peak Load and Kilowatt-Hours check boxes as desired.
3. Click Apply.
Configure and Control Outlet Groups
Outlet group terminology
An outlet group consists of outlets that are logically linked together on the same Rack
PDU. Outlets that are in an outlet group turn on, turn off, and reboot in a synchronized
manner:
•A local outlet group consists of two or more outlets on a Rack PDU. Only the outlets
in that group are synchronized.
•A global outlet group consists of one or more outlets on a Rack PDU. One outlet is
configured as a global outlet, which logically links the outlet group to outlet groups
on up to three other Rack PDUs. All outlets in the linked global outlet groups are
synchronized.
For global outlet groups, the initiator outlet group is the group that issued the
action.
For global outlet groups, a follower outlet group is any other outlet group that is
synchronized with the initiator outlet group.